境外投资项目审批流程
第二篇:16.项目审批流程
6. 企业投资项目审批流程图
The enterprise investment project approval flow chart
1. project applying
2. Project register and filing for record to get project approve notice from “Dalian city development and Reform Bureau”.
? The water and soil conservation program and water intake permission for examination and approval from “Dalian city water Resource bureau”.
? Project environment impact assessment for examination and approval from “Dalian Municipal Environmental Protection Bureau”.
? Project location assessment from “Dalian Urban Planning Bureau”.
? Pre-examination to the project use land from “Dalian City Land Bureau”.
? Opinion from other relates Bureau or Departments.
3. Enterprise investment project approval from “Dalian city development and Reform Bureau” .
-------------------------------------------- Project plane planning and design.
4. Construction land use planning permit from “Dalian Urban Planning Bureau”.
-------------------------------------------- The initial design scheme.
5. “Dalian City Land Bureau”.
6. The project will be reviewed by “The construction project Joint Commission”.
-----------------------------------The engineering draw design and review. 7.
? Lighting design effect review from “Comprehensive Law Enforcement Bureau”.
? Lightning protection equipment audit from “Meteorological Bureau”.
? Fire-fighting design review from “fire brigade”.
? The civil air defense construction approval from “Civil Air Defense Office”.
? Design and construction drawing check from “The planning department”.
? Development project review from “The development Department”.
8. Administrative charges from “Dalian Finance Bureau”.
9. To get “Construction project planning permit” from “Dalian Urban Planning Bureau”.
10.
? Bidding (“Dalian City bidding Office”).
? Quality supervision and procedures from “Dalian Municipal Quality Supervision Station”.
? Safety supervision and procedures from “Dalian City security station”.
11. Construction engineering construction permit from “Dalian city planning and Construction Bureau”.
12. To get the “Construction Engineering Actinomyces task book” from “Dalian city planning and Construction Bureau”.