房建工程监理工作总结
一、 工程概况
房建Ⅰ标:*综合楼建筑面积1200平方米,三层框架结构,局部四层,建筑高度14.9米,设计耐久年限50年,结构抗震设防烈度八度,结构等级二级,框架抗震等级二级,丙类建筑,基础采用人工成孔灌注桩基础。锅炉房建筑面积109.6平方米,为一层砖混结构,建筑高度6米,结构抗震设防烈度八度,结构等级二级。基础形式为墙下钢筋混凝土条形基础,地基处理为基础底3:7灰土夯实500mm。变电所建筑面积96.1平方米,为一层砖混结构,建筑物高度6.2米,结构抗震设防烈度八度,结构等级二级。
*综合楼建筑面积1200平方米,三层框架结构,局部四层,建筑高度14.9米,设计耐久年限50年,结构抗震设防烈度八度,结构等级二级,框架抗震等级二级,丙类建筑,基础采用人工成孔灌注桩基础。锅炉房建筑面积109.6平方米,为一层砖混结构,建筑高度6米,结构抗震设防烈度八度,结构等级二级。基础形式为墙下钢筋混凝土条形基础,地基处理为基础底3:7灰土夯实500mm。变电所建筑面积96.1平方米,为一层砖混结构,建筑物高度6.2米,结构抗震设防烈度八度,结构等级二级。
*综合楼建筑面积1200平方米,三层框架结构,局部四层,建筑高度14.9米,设计耐久年限50年,结构抗震设防烈度八度,结构等级二级,框架抗震等级二级,丙类建筑,基础采用钢筋混凝土柱下条形基础。锅炉房建筑面积109.6平方米,一层砖混结构,建筑高度6米,结构抗震设防烈度八度,结构等级二级。基础形式为墙下钢筋混凝土条形基础,地基处理为基础底3:7灰土夯实500mm。变电所建 1
筑面积96.1平方米,为一层砖混结构,建筑物高度6.2米,结构抗震设防烈度八度,结构等级二级。
*综合楼建筑面积2098平方米,三层框架结构,局部四层,建筑高度14.9米,设计耐久年限50年,结构抗震设防烈度八度,结构等级二级,框架抗震等级二级,丙类建筑,基础采用钢筋混凝土柱下条形基础。锅炉房建筑面积109.6平方米,一层砖混结构,建筑高度6米,结构抗震设防烈度八度,结构等级二级。基础形式为墙下钢筋混凝土条形基础,地基处理为基础底3:7灰土夯实500mm。变电所建筑面积125平方米,为一层砖混结构,建筑物高度6.2米,结构抗震设防烈度八度,结构等级二级。
*:综合楼建筑面积4003.8平方米,三层框架结构,局部四层,建筑高度15.00 m,设计耐久年限50年。结构抗震设防烈度八度,结构等级为二级,框架抗震等级二级,丙类建筑。基础采用钢筋砼井桩基础。锅炉房建筑面积19604平方米, 一层砖混结构。 变电所建筑面积130平方米,一层砖混结构。公 厕建筑面积 2 ×99平方米, 一层砖混结构。洗车及修理建筑面积2×269平方米,一层砖混结构。
*:综合楼建筑面积2098平方米,三层框架结构,局部四层,建筑高度14.85米,设计耐久年限50年。结构抗震设防烈度八度,结构等级二级,框架抗震等级二级,丙类建筑,基础形式为人工成孔钢筋混凝土灌注桩基础。锅炉房建筑面积109.6平方米,一层砖混结构。变电所建筑面积125平方米,一层砖混结构;养护工区综合楼建筑面积685平方米,三层框架结构,局部四层,建筑高度14.85米,设计耐久年限50年。结构抗震设防烈度八度,结构等级二级,框架抗震等级二级,丙类建筑,基础形式为人工成孔钢筋混凝土灌注桩基础。锅炉房建筑面积60平方米,一层砖混结构,变电所建筑面积96平方 2
米,一层砖混结构。
工程造价:Ⅰ标段工程造价14763358.00万元
Ⅱ标段工程造价10621435.00万元
Ⅲ标段工程造价8820820.00万元
建设单位:* 质监单位:* 勘察单位:甘
肃省交通规划勘察设计研究院
设计单位:*
监理单位:*
施工单位:(房建Ⅰ标段)* (房建Ⅱ标段)*
(房建Ⅲ标段)*
二、 监理工作部署
我监理方选派监理工作经验丰富、认真负责的监理工程师*同志为高级驻地,*同志为副高级驻地,并*组成项目监理工作机构;在刚开工时事务繁多,我监理工程师*同志努力为开工前做好准备工作,后因身体原因不能继续工作,我监理公司调任国家注册监理工程师*同志为高级驻地,对本工程进行施工阶段监理。由监理工程师高君教同志和李丹雷同志对本项目编制了详细的监理规划;重点突出了施工过程中的关键和施工难点的监理手法和监理细则。保证使监理工作有效、顺利地开展,从而更好地维护业主的合法权益。
三、 监理工作依据
1、 工程施工图纸、图纸会审纪要、地质勘察报告及其它设计文
件;
3
2、 工程施工合同、委托监理合同;
3、 建设工程施工质量验收规范及工程建设标准强制性条文;
4、 建设工程监理规范;
5、 国家现行的相关法律、法规、规范、标准等。
四、 主要的质量监理控制情况
五、 1. 条形基础、桩基础的质量监理
① 本工程王家山、刘寨柯两个工地基础处理采用钢筋混凝土柱下条形基础,在各基坑开挖后,现场监理人员均对每一个基坑底土质进行检验,坑底土质无浮土,并且较为完好的情况下,进行施工,以确保工程质量。
② 本工程其它四个施工点基础采用井桩基础、混凝土灌注桩基础,在基础开挖时,严格审核施工单位桩基础开挖方案。
2. 原材料的质量控制
本工程采用的钢材、水泥、红砖、砂、石等均经现场见证取样,送中心试验室检验合格后使用,并且以上材料均具备合格证及产品的认证证书,而在施工后期,铝合金门窗、PVC管材管件、外墙瓷砖、玻璃等在进场时均在现场检验来料,确认该材料使用符合设计要求及施工规范要求后,并核查该产品的合格证书及产品认证证书,才允许进入施工使用。在浇筑砼及砌筑砖砌体过程中,现场监理人员能及时 4
做好现场见证取样工作,施工单位积极配合工作,确保了施工用料合理规范。
3. 钢筋砼工程的控制
钢筋砼工程的每一个工序的开始和结束,都由施工单位提出和自检,然后经现场监理人员检查、审核,质量符合施工、设计要求,并具备下一个工序开始的条件下,方许可下一工序的施工。在支模过程中,检查其模板标高、模板尺寸、支撑、模板面清洁等,并在钢筋绑扎前完成该层模板核查,确认该层支模完全按照设计图纸及相关设计修改通知进行施工,从而保证支模过程与钢筋绑扎的顺利过渡。在钢筋制作前,对钢筋下料表进行严格审查,并且对钢筋制作过程中严格把关其锚固长度、搭接长度、焊接部位直径。在钢筋绑扎安装过程中未发现施工单位有偷漏钢筋现象。砼浇筑过程是监理人员进行质量控制的关键。由于后期为赶工期晚上加班,故要求施工单位提供详细的施工浇砼方案,并要求施工单位仔细检查模板支撑系统,保证施工过程安全,经审查批准后,方同意浇筑砼,在现场搅拌砼下料时,严格要求施工队按设计配合比下料。由于施工单位积极配合,监理工作能落到实处。从拆模后察看,有局部麻面现象,都经监理人员督促进行处理。各楼层砼试压件检验报告,均达到设计强度要求。
4. 建筑装饰装修工程的质量控制
5
在进入内、外装饰工程前,已要求施工单位做好样板,并让施工单位向下属相关班组进行质量技术交底。开始进行施工时质量控制工作有些失控,主要原因是因为施工单位内部管理不协调、质量意识不高,使监理平行检验发现的问题得不到较好的执行,在各层内抹灰都出现不同程度的手尾,影响施工质量。后来现场监理人员的督促下,质量状况得到明显的控制。外墙面质量较好,平整度、垂直度都表现良好。
楼地面施工前,基底处理得较好,经现场检查结构层与水泥砂浆层得到较好连结。在施工过程中,控制其砂浆配合比、用水量等,特别是不允许施工队采用人工搅拌取代机械搅拌,从而保证砂浆拌和均匀。由于控制严格,该工序质量良好。
在制作木门、铝合金窗,已要求施工单位提供相关材料的合格证、产品认证证书、材料进场前已由现场监理人员做好进场检验。门窗制作和安装表现都达到设计要求。
五、 施工安全与文明的控制
施工单位对各班组进行的三级安全教育、安全技术交底、班前安全学习工作执行得比较好,并派专人专职负责。每天施工单位均做好配电箱、各种机械的安全检查和记录。现场工地施工人员普遍安全意识及觉悟不够高,不戴安全帽、电缆拖地、电源线乱拉乱接等现象时有发生,但经现场监理人员多次督促纠正,得到明显改善。施工用电、 6
工棚宿舍用电能严格按要求使用。在文明施工方面,有时现场积水未能及时清除,以及楼梯口未安全封蔽,对文明施工影响较大,后经督促,杜绝了这种现象。其余方面施工队都做得较好。
六、 进度投资的控制
现场监理人员每月都要求施工单位提供当月工、料、机动态月报、施工任务完成情况月报,及下一个月的施工进度详细计划,经报审核定后,由施工单位按施工计划执行。在施工过程中,及时跟踪施工进度,对比计划进度状况,保证施工进度计划的顺利实施,掌握工程建设资金去向情况。经审核后,核实当月施工实际完成情况及施工图变更情况,反映予甲方。每次经审核工程进度情况后,据实签付工程款。
七、工程质量验收评定
*高速公路房建工程分为三个标段六个项目工程,各项目工程包含综合楼、锅炉房、变电所等单位工程以及其它附属建(构)筑物与室外工程,分别于20xx年6月2日及7月13日进行了基础及主体结构验收,均验收合格,并于20xx年11月21日我监理单位组织各专业监理工程师进行了工程竣工预验收,对存在的一些问题要求施工单位整改或修补,整改后经检查验收,各单位工程六大分部工程即地基与基础、主体结构、建筑装饰装修、建筑屋面、建筑电气、建筑采暖及给排水均评定为合格,工程质量符合设计及施工质量验收规范要 7
求,工程实体满足安全及使用功能要求,质量控制资料经基本齐全、有效,各单位工程总体评定为合格,同意验收。
八、 监理工作经验总结
现场施工监理过程中,监理人员自身素质、业务水平非常重要,要知道监理人员自身就要代表监理公司对施工单位行使监理权,所以监理人员形象、素质就代表监理公司的形象。在本工程施工期间,现场项目监理机构一直常驻现场,在施工期间,严格执行工程开工审批和分部工程开工审批,材料进场报验,材料、试件见证取样,随机抽检,分项工程检验批验收,分部工程验收,平行检验,巡检等质量控制措施和质量控制程序,高效率、高要求地监控施工过程。遵循“专业、专心、专注”,“严格监理,热情服务“的宗旨,以顾客为关注焦点,更好的提供监理服务,让我们在今后的工作中,逐步提升我们的监理业务水平。
总监理工程师:
*工程驻地监理办
8
第二篇:市政道路工程监理工作总结-[1]
XX新建道路工程
监理工作总结
编制:________________
审核:________________
审批:_______________
四川省城市建设工程监有限公司
20xx年2月19日
目 录
一、工程概况 ······················································································································ 1
二、监理组织机构和设施投入 ·························································································· 1
三、合同和信息管理 ·········································································································· 2
四、施工概况及对承包商的评价意见 ·············································································· 2
五、工程质量控制及评价意见 ·························································································· 2
(一)施工准备阶段的质量控制 ··············································································· 2
(二)施工阶段质量控制 ··························································································· 3
(三)资金投资控制 ··································································································· 4
(四)竣工验收阶段质量控制 ··················································································· 4
六、施工阶段的工程进度控制 ·························································································· 4
七、施工阶段工程投资控制 ······························································································ 5
八、安全、文明施工控制 ·································································································· 5
九、体会、经验、建议 ······································································································ 5
Xx新建道路工程
监理工作总结
一、工程概况
工程名称:xx新建道路工程
建设单位:苍溪县城乡建设与规划局
设计单位:xx市政工程勘测设计研究院
监理单位:四川省城市建设工程监理有限公司
施工单位:南部县兴发建设工程有限公司
工程内容:本工程雨水管道一条、污水管道两条、污水压力管线一条,位于郑州市木木地方。道路全长2000米,道路宽60米,双向八车道。路面结构采用18厘米厚石灰水泥稳定土,36厘米厚水泥粉煤灰稳定碎石,6厘米厚粗粒式沥青混凝土,5厘米厚中粒式沥青混凝土,4厘米厚细粒式沥青混凝土。0.6厘米厚乳化沥青下封层(不计厚度)
计划工期:360天
质量目标:合格
工程投资:1700万元
二、监理组织机构和设施投入
本工程成立由 李洪波 任总监理工程师,由 宋明 任总监理工程师代表,杨晓斌 任专业监理工程师, 赵跃 任监理员的组织机构,总监受公司委托和业主授权全面负责本工程的监理工作,总监
- 1/6 -
代表、专业监理工程师和监理员行使各自的职责。
根据本工程特点,为了便于更好地完成监理工作,特自备全站仪、水准仪各一台,电脑一套,打印机一台及其他检测工具等,从开展监理工作中已证实可以满足需要。
三、合同和信息管理
监理项目部在合同和信息管理方面主要注重以下几方面工作:首先,进行与项目有关的各类合同的跟踪管理,包括对合同各方执行情况进行检查;负责项目实施过程中各类信息的收集、分类存档和整理。其次,随时向业主提供工程投资、质量、进度、安全及合同等方面的信息情况,并每月提供月报和报告;建立工地例会会议制度,整理各类会议纪录;督促承包商及时整理工程技术资料档案等,这些工作的开展为工程的顺利进行起到了积极作用。
四、施工概况及对承包商的评价意见
施工方对工程质量较为重视,各工序完工自检后能按照规范要求组织相关单位验收合格后再进入下道工序施工;建立了完备的质量保障体系和质检制度,对构配件及应送检项目材料积极配合我监理单位相关人员进行抽样送检,所送检材料检验合格,能用于本工程;内业资料及时跟进,对监理工程师指出的问题能及时采取措施进行整改,有力地保障了工程质量。
五、工程质量控制及评价意见
(一)施工准备阶段的质量控制
首先,监理方认真熟悉了解合同文件、设计图纸及技术文件,对承包商提交的施工组织设计及施工计划、施工方案进行了审查,参加了设计交底、工地交桩以及图纸会审。
参加了对工程基准线、坐标网、控制桩和水准点的现场交底,并对水准点、控制点进行了复核。检查了开工条件,如承包商工、料、机落实、进场情况;水泥、砂、石料及预制管构件、主要外购件的质
- 2/6 -
量及有关复试资料,对部分供应厂家进行了实地考察,见证了复试试验,构配件质量满足设计及规范要求,适用于本工程。
召开首次工地会议,明确了施工过程中业主、承包商、监理方三方各自的职责和监理工作管理办法。编制了详细的《监理规划》、《监理细则》,为我们开展监理工作打下了基础。
(二)施工阶段质量控制
在施工中要求承包商建立起完善的质量检测体系,必须在自检合格的基础上通知相关主体单位验收,经监理签认后,方能进入下道工序施工。
督促施工单位做好道路施工水准点、控制点、基准线的测量、复核管道中心定位、复核工作,并检查其有关记录,在施工单位上报复测资料的基础上,对临时水准点等进行了复核,其结果均在误差范围内。同时,多次抽检了道路、管道中线的控制点、中心桩、检查井位置,确保其准确性。
在沟槽开挖工序中,检查了承包商沟槽开挖坡度、安全,沟槽排水、支撑措施是否落实,重点控制沟槽不得受水浸泡,防止槽底土体扰动和超挖。
会同业主、地勘、质检、施工等五方主体对沟槽进行验收,验收过程各数据我方均做详细记录,在抽检垫层、平基的厚度及高程无误后,才允许施工单位进入管道安装工序的施工工作。
管道安装工作重点检查管底坡度是否倒流水,管道中心线位置是否符合设计要求,并对管内底高程进行检测,同时,随机抽取了以上各道工序的混凝土质量,见证了试块试压,全部达到设计要求。
通过巡视的手段,对全线检查井砌筑质量进行检查,发现有通逢、灰浆不饱满,抹面有空鼓、裂缝等现象的,均要求施工单位返工,质量达到相关规范要求。承包商充分意识到回填质量的重要性,
- 3/6 -
本次工程的回填土施工单位均自觉分层夯实,我监理方见证了回填土压实度试验,回填过程中现场监理全程旁站,严把质量关,回填土压实度达到了设计及规范要求。
(三)资金投资控制
根据工程实际情况,对工程中采用的原材及构配件进行多方价格对比考察,要求施工单位使用质量达标,价格适中的产品。
根据设计文件结合现场实际情况,对道路换填、挡墙、沟槽开
挖、新增零星项目、施工便道的各类数据反复核对,按实际情况签证,并做好相应影像资料的存档工作。
(四)竣工验收阶段质量控制
根据设计及相关规范要求,在施工单位自检合格的基础上,会同相关单位对所有井段分段做闭水试验,试验结果渗水量均在允许范围内,符合设计及规范要求。
六、施工阶段的工程进度控制
进度控制的总任务就是在满足工程建设总进度计划要求的基础上,编制或审核施工进度计划,并对其执行情况加以动态控制,跟踪检查施工项目按期竣工并交付使用。我方工作重点是审核承包商提交的施工进度计划。要求施工总进度计划应确定分期分批完成的项目组成,各工程项目的开工、竣工顺序及时间安排,全场性准备工作,特别是首批准备工作的内容与进度安排等。随时了解进度计划执行过程中所存在的问题,并帮助承包商给予解决,特别是承包商无力解决的内外关系协调问题。及时检查承包商报送的施工进度计划报表和分析资料,同时进行现场实地考察,核实所报送的已完项目的时间及工程量,在对工程实际进度资料进行整理的基础上,我方将其与计划进度对比,以判定实际进度是否出现偏差。如果出现偏差,我方进一步分析此偏差对进度控制目标的影响程度及产生的原因,以便研究对策,提出纠偏措施,对承包商申请的已完工程分项工程量进行核实,在监理工程师通过检查验收后签发工程进度款支付凭证。
- 4/6 -
七、施工阶段工程投资控制
本工程投资控制的原理是把计划投资额作为投资控制的目标值,在工程施工过程中定期进行投资实际值与目标值比较,通过比较发现并找出实际支出额与投资控制目标值的偏差,然后分析产生偏差的原因,并采取有效措施加以控制,以保证投资控制目标的实现。首先,我方熟悉图纸、设计要求、标底标书,分析合同价构成因素,明确工程费用最易突破的部分和环节,从而明确投资控制的重点。并审查承包商提交的工程预算,定期、不定期进行工程费用超支分析,并提出控制工程费用突破的方案和措施。认真、慎重对待工程变更、设计修改,严格经费签证,及时对完工工程量进行计量,及时签证支付进度款。
八、安全、文明施工控制
安全、文明施工是保证工程能否顺利地在额定工期内按时、保质完成的重要条件。我方对此紧抓不懈,督促承包商在施工中认真贯彻“安全第一,预防为主”和坚持“管生产必须管安全”的原则。我方督促参加施工的人员必须接受安全技术教育,熟知和遵守本工种的各项安全技术操作规程,并要求定期进行安全技术考核,对特殊工种操作人员,我方检查其特殊工种合格证后,才能上岗作业。
操作人员上岗前,要求必须按照规定穿戴防护用品,督促施工负责人和安全检查员随时检查劳动防护用品的穿戴情况,并组织人员定期检查和验收施工所用的各种机具设备、劳动保护用品和电器设备等,保证其处于完好状态。
九、体会、经验、建议
1、业主的支持是保证工程顺利完成的基础:在整个施工过程中业主领导对监理方在各方面都给予了大力的支持和协助,积极支持监理方的各项管理措施和监理手段,为工程的顺利完成提供了保证。
2、协调、沟通的重要性:在项目实施过程中,有很多的协调沟通工作要做,一个成功的监理项目部既要严格监理工程,也要同承包商建立良好的监理和被监理的合作关系,站在不同的角度为了一个共同
- 5/6 -
目的,做好各自工作,只有这样才能出色地控制好质量、进度、投资等各项指标。
3、监理项目部自身建设:监理工作需要丰富的现场管理经验和扎实的理论水平,综合素质要求很高,要做一个优秀的监理工作者,只有取彼之长,补己之短,在工作中不断提高自身素质,更好地把监理工作做好。
四川省城市建设工程监理有限公司
20xx年2月19日