刘秀秀020512013
赵明明020512041
Minutes of Chemical Seminar
The seminar was held on Tuesday, May 25, 2010, 2010, at 8:00a.m. at Brand Road, the P&O university.
Present: Mr. Sunny Brown, Mr. Alex Jester, Miss Jenny Skies, Mr. Douglass Seaton, Mr. George Alexander, Miss Donna Ryan. Absent: Mr. Hall Franks, Miss Sophie Freda.
Moderator: Mr. Mike Hillman.
The main points:
1. Mr Mike Hillman, the president of seminar, presented the work and activity situation in seminar and got warmly discussed. Then the report passed after the modification on some contents.
2. The seminar agreed to pass a quarterly publication, which named chemical study and would be launched in July. Mr. Mike Stanley was nominated as Chief Editor and he appreciated it.
3. The participants agreed to hold a short-term training class for training chemical professional talents. It will recruit students next summer. Miss Sophie Freda is appointed to be the director of admission office.
4. The seminar recommended to invite scholars and experts to make academic speech so that communication of technology &
experience could be strengthened. Mr. Mitchell would in charge of the job.
5. The seminar elected a new executive agency. Mr. Alexander was voted to be the new president of seminar. His term of service would started next June. Participants applauded warmly when he was elected. Then he presented brief conversation to show thanks to everyone and promised to fulfill his responsibility. Attendees expressed the great appreciation to the present president for his excellent job to the seminar.
6. The elected president, Mr. Alexander , claimed that the general meeting would be held on June 10, the next year and then he would declare his work plan.
7. The seminar decided to collect new members.
8. The seminar is closed at 10:00 a.m.
Minutes submitted by Secretary, Donna Ryan.
第二篇:分包商合同终止会议-会议纪要-英文版
MINUTES OF SECOND SITE MEETING --Of The Special Committee
Date: October 20th, 2012
Time: 12:00-16:30
I. Venue: Site Office OfMaseed
II. AttendeeOf The Meeting
A. Consultant:
? Mr. XXX—Deputy R.E.
? Mr. XXX—Inspector
B. Main Contractor:
? Mr. XXX—Project Manager
? Mr. XXX—Office Administrator
C. Sub-Contractor:
? Mr. XXX-- Project Manager
? Mr. XXX—Accounting Manager
? Mr. XXX—Surveyor
? Mr. XXX—Material Engineer
III. Main Issues Of The Meeting
A. The Site Works
a. Consultant:
The Deputy R.E. of the Consultant, Mr. XXX declares that the second Site Meeting Of The Special Committee start at 12:00 in the morning and welcome all the attendee of the Meeting.
Mr. XXX firstly gives a general introduction about the Project and the Remaining Issues after the first Site Meeting of The Special Committee and then he requests the Sub-Contractor gives detailed information about the works on the site and the progress of the rectification since last Meeting. b. Sub-Contractor:
Page 1 / 3
The Project Manager Of the Sub-Contractor, Mr. XXXputs forward the list of Status On Site according to the requirements of the Consultants and states that they have completed all the under processing works on the site and rectified all the defects that have been remarked during the inspection of last Site Meeting.
c. Main Contractor:
The Project Manager Of The Main Contractor, Mr. XXX points out that there still exist some defects in the works of the Sub-Contractor after hearing about the statements of Mr. XXX. For example, there is one check point (K139+900) less 5cm than the specification for the Top Embankment and there still exist some weeds on the road surface from K124+000 to K129+000 ect. However, the Main Contractor still can accept the works that have been handed over to him.
B. The Works From K141+000 To K145+000
a. Consultant:
The Deputy R.E. of the Consultant, Mr. XXX states that though the Sub-Contractor has completed the works for the Clearing and Grubbing, Stripping and NGL Compaction for the section from K141+000 to K145+000 before, all the area has grown up lots of grasses again. Therefore, all the works that have been done should be repeated again. However, the Main Contractor still could give some allowance for the works that have been done by the Sub-Contractor.
b. Main Contractor:
After some consulting with the Consultant and the Sub-Contractor, the Main Contractor finally agrees with that all the works done in the section from K141+000 to K145+000 should be paid by 50% of itsOriginal Quantities, including the Clearing & Grubbing, Stripping and NGL Compaction.
C. Service Road From K141+000 To K143+000
a. Sub-Contractor:
The Project Manager Of the Sub-Contractor, Mr. xxx states that the Sub-Contractor has constructed the Service Road from K141+000 to K143+000 additionally and requested some compensation from the Main Contractor.
b. Main Contractor:
The Main Contractor refuses the request of the Sub-Contractor and states Page 2 / 3
that there is no any pay item in the Bill Of Quantities for the Service Road Construction and the worksare just the precondition to execute the Project.
D. Final Interim Payment For The Project
The Deputy R.E. of the Consultant, Mr. xxx states that the Final Interim Payment of the Project should be prepared according to the Agreements between the Main Contractor and the Sub-Contractor during the Meeting and the Final Quantities of the Payment also should be viewed and approved by the Consultant.
IV. Conclusion
Finally, the Deputy R.E. of the Consultant, Mr. xxx announces that the Sub-Contract between the Main Contractor and the Sub-Contractor could be terminated according to the sprite of the Committee and the Committee has realized its special aims completely.
_____________________ ____________________
For The Consultant For The Main Contractor
Eng. XXX Eng. XXX
____________________
For The Sub-Contractor
Eng. XXX
Attachment:
1. Attendance Sheet Of The Site Meeting
2. Appointment For The Project Manager Of Sub-Contractor
3. Status On The Site
4. Final Interim Payment For The Project
Page 3 / 3