会议记录英文版

时间:2024.3.27

刘秀秀020512013

赵明明020512041

Minutes of Chemical Seminar

The seminar was held on Tuesday, May 25, 2010, 2010, at 8:00a.m. at Brand Road, the P&O university.

Present: Mr. Sunny Brown, Mr. Alex Jester, Miss Jenny Skies, Mr. Douglass Seaton, Mr. George Alexander, Miss Donna Ryan. Absent: Mr. Hall Franks, Miss Sophie Freda.

Moderator: Mr. Mike Hillman.

The main points:

1. Mr Mike Hillman, the president of seminar, presented the work and activity situation in seminar and got warmly discussed. Then the report passed after the modification on some contents.

2. The seminar agreed to pass a quarterly publication, which named chemical study and would be launched in July. Mr. Mike Stanley was nominated as Chief Editor and he appreciated it.

3. The participants agreed to hold a short-term training class for training chemical professional talents. It will recruit students next summer. Miss Sophie Freda is appointed to be the director of admission office.

4. The seminar recommended to invite scholars and experts to make academic speech so that communication of technology &

experience could be strengthened. Mr. Mitchell would in charge of the job.

5. The seminar elected a new executive agency. Mr. Alexander was voted to be the new president of seminar. His term of service would started next June. Participants applauded warmly when he was elected. Then he presented brief conversation to show thanks to everyone and promised to fulfill his responsibility. Attendees expressed the great appreciation to the present president for his excellent job to the seminar.

6. The elected president, Mr. Alexander , claimed that the general meeting would be held on June 10, the next year and then he would declare his work plan.

7. The seminar decided to collect new members.

8. The seminar is closed at 10:00 a.m.

Minutes submitted by Secretary, Donna Ryan.


第二篇:分包商合同终止会议-会议纪要-英文版


MINUTES OF SECOND SITE MEETING --Of The Special Committee

Date: October 20th, 2012

Time: 12:00-16:30

I. Venue: Site Office OfMaseed

II. AttendeeOf The Meeting

A. Consultant:

? Mr. XXX—Deputy R.E.

? Mr. XXX—Inspector

B. Main Contractor:

? Mr. XXX—Project Manager

? Mr. XXX—Office Administrator

C. Sub-Contractor:

? Mr. XXX-- Project Manager

? Mr. XXX—Accounting Manager

? Mr. XXX—Surveyor

? Mr. XXX—Material Engineer

III. Main Issues Of The Meeting

A. The Site Works

a. Consultant:

The Deputy R.E. of the Consultant, Mr. XXX declares that the second Site Meeting Of The Special Committee start at 12:00 in the morning and welcome all the attendee of the Meeting.

Mr. XXX firstly gives a general introduction about the Project and the Remaining Issues after the first Site Meeting of The Special Committee and then he requests the Sub-Contractor gives detailed information about the works on the site and the progress of the rectification since last Meeting. b. Sub-Contractor:

Page 1 / 3

The Project Manager Of the Sub-Contractor, Mr. XXXputs forward the list of Status On Site according to the requirements of the Consultants and states that they have completed all the under processing works on the site and rectified all the defects that have been remarked during the inspection of last Site Meeting.

c. Main Contractor:

The Project Manager Of The Main Contractor, Mr. XXX points out that there still exist some defects in the works of the Sub-Contractor after hearing about the statements of Mr. XXX. For example, there is one check point (K139+900) less 5cm than the specification for the Top Embankment and there still exist some weeds on the road surface from K124+000 to K129+000 ect. However, the Main Contractor still can accept the works that have been handed over to him.

B. The Works From K141+000 To K145+000

a. Consultant:

The Deputy R.E. of the Consultant, Mr. XXX states that though the Sub-Contractor has completed the works for the Clearing and Grubbing, Stripping and NGL Compaction for the section from K141+000 to K145+000 before, all the area has grown up lots of grasses again. Therefore, all the works that have been done should be repeated again. However, the Main Contractor still could give some allowance for the works that have been done by the Sub-Contractor.

b. Main Contractor:

After some consulting with the Consultant and the Sub-Contractor, the Main Contractor finally agrees with that all the works done in the section from K141+000 to K145+000 should be paid by 50% of itsOriginal Quantities, including the Clearing & Grubbing, Stripping and NGL Compaction.

C. Service Road From K141+000 To K143+000

a. Sub-Contractor:

The Project Manager Of the Sub-Contractor, Mr. xxx states that the Sub-Contractor has constructed the Service Road from K141+000 to K143+000 additionally and requested some compensation from the Main Contractor.

b. Main Contractor:

The Main Contractor refuses the request of the Sub-Contractor and states Page 2 / 3

that there is no any pay item in the Bill Of Quantities for the Service Road Construction and the worksare just the precondition to execute the Project.

D. Final Interim Payment For The Project

The Deputy R.E. of the Consultant, Mr. xxx states that the Final Interim Payment of the Project should be prepared according to the Agreements between the Main Contractor and the Sub-Contractor during the Meeting and the Final Quantities of the Payment also should be viewed and approved by the Consultant.

IV. Conclusion

Finally, the Deputy R.E. of the Consultant, Mr. xxx announces that the Sub-Contract between the Main Contractor and the Sub-Contractor could be terminated according to the sprite of the Committee and the Committee has realized its special aims completely.

_____________________ ____________________

For The Consultant For The Main Contractor

Eng. XXX Eng. XXX

____________________

For The Sub-Contractor

Eng. XXX

Attachment:

1. Attendance Sheet Of The Site Meeting

2. Appointment For The Project Manager Of Sub-Contractor

3. Status On The Site

4. Final Interim Payment For The Project

Page 3 / 3

更多相关推荐:
会议记录英文版

TherecordsoftheregularconferenceofthelivingstudyingministryYanyuanbranch20xx926participantsMinisterNiethenewcomersC...

英语会议记录模版

MeetingrecordProjectnamemakethereportDateofmeetingMay1320xxMinutespreparedbyZhangHuizhuanChargetimeto20minutes1Purp...

如何写外企的英文会议记录(样本)WORD

这里是一份外企的英文会议记录样本供涉外企业的文秘人员参考17Aug20xx会议举行的日期XXXCOMPANY8THMEETINGOF20xxMinutesofmonthlymeetingheldatthehea...

minutes 会议记录英文版

MinutesofmeetingLCPaperNOCB1630001RefCB1PLITB1LegislativeCouncilPanelonInformationTechnologyandBroadcastingMinuteso...

Meeting minutes会议记录英文版

MeetingminutesDate17thSeptember20xxAddress2203RoomConductorHeadmasterMrWenPresent42studentsAbsentLiJiangO...

minutes_会议记录英文版1

MinutesofmeetingGroupTwoMinutesofmeetingHeldonThursday11April20xxat830amIntheLibraryofZhejiangAgricultureandForestr...

会议纪要(英文版)

说明Remark1指PE内部服务器上的项目编号GivenbyPEDCCegC12012会议编号MeetingNo统一会议纪要编号规则UnifiedNumberingRulesforMOM内部InternalCX...

英文版法律顾问手册-董事会会议记录

MINUTESOFMEETINGOFDIRECTORSYOURCOMPANYNAMEOpeningMinutesofameetingoftheBoardofDirectorsofYOURCOMPANYNAMEdulycalleda...

职场商务英语写作:会议记录常用缩写符号及含义大全 via安格英语

在线英语培训领导者英语口语如何提高语言环境很重要英语口语训练营免费体验webrecentcurriculum职场商务英语写作会议记录常用缩写符号及含义大全职场上大家都经历过大大小小的会议一般来说会议后都会有组织...

英语组11月第三周会议记录

中国教育培训领导品牌美国纳斯达克上市机构英语组周会会议记录使命责任分享学习第1页共3页中国教育培训领导品牌美国纳斯达克上市机构使命责任分享学习第2页共3页中国教育培训领导品牌美国纳斯达克上市机构使命责任分享学习...

英语组教研活动会议记录

星火教育英语教研活动会议记录主持人杨雪花记录吴玉玲参加人员英语组全体教师教研组全体成员缺席人员无会议内容一会前准备抽签决定讲课教师的顺序二主持人精彩开场老师及相关评委点评中场游戏环节中场休息两位老师讲课听课老师...

小学英语教研组会议记录

英语教研组活动记录

英文版会议记录(22篇)