定额调差表(参照贵州省2004建筑与装饰工程量清单报价手册)
一、A6.1.1钢屋架(P151)
(一)定额010601002-001
1、人工费调差:
(53-26)*36.97=998.19
2、材料费调差
(1)钢管:(7200-4800)*0.761=1826.4
(2)钢球:(14025-9350)*0.117=546.975
(3)锥头钢板:(9300-6200)*0.057=176.7
(4)支座托钢板:(7800-5200)*0.021=54.6
(5)封头圆钢:(5700-3800)*0.018=34.2
(6)六角钢:(5550-3700)*0.026=48.1
(7)高强螺栓:(13.35-8.9)*21.64=96.298
(8)紧钉:(2-1)*38=38
(9)电焊条T422:(8.5-5.41)*26=80.34
(10)氧气:(5-2.17)*9.75=27.59
(11)乙炔:(22.7-15.4)*3.9=29.52
(12)普通松锯材:(1455-970)*0.005=2.425
(13)红丹防锈漆:(17.4-11.6)*8.55=49.59
(14)调和漆: (12-7.7)*6.32=27.176
(15)汽油90#:(8.48-4.29)*1.5=6.3
3、机械费调差
(1)载重汽车8t以内:(1000-435.52)*0.39=220.15
(2)交流弧焊机32KVA:(150-102.65)*1.93=91.39
(3)其他机械费:(1.5-1)*325=162.5
此项定额调差后价格为(不含管理费及利润):
A=(961.22+998.19)+(5984.54+3044.21)+(692.97+474.04)=12155.17,其中人工费:1959.41,材料费:9028.75,机械费:1167.01