CONTENTS
A. Statement of Claim
B. Attachments
1. Correspondence
2. Daily pipe jacking record
3. Daily diary
4. Photograph
5. Additional cost for pipe jacking from S17-S18
6. Schedule of day-work
7. Diagram indicating method of working for DN 3000 pip jacking
8. List of pipe jacking equipment
Statement of Claim
1. Summary of Claim
Request for Extension of Time and Reimbursement of Additional Costs pursuant to Clause 12.2 in respect of encountering unforeseeable underground obstructions whilst Pipe Jacking DN3000 pipes between Shafts S17-S18
10 days for extension of time
3,344,270,012VND for additional cost
2. Introduction
DN3000 Pipe Jacking Shafts S17 to S18 has a total span of 189.4m and is included in Section 1 Part C of the works.
The break-out of the boring machine started on 24 March 2006, and first pipe was jacked on 28th March 2006.
…… …… 余下全文